What would you like to improve in the village? Suggest a public-space improvement, a service or a community project. The watchdog team will review it; submission does not publish it automatically.

06 / Municipal and regional projects

From decision to outcome.

For each project, we distinguish plans, approved funding and documented outcomes. This selection includes heritage and recent projects; it is not the municipality’s complete investment register.

2024
Opened on 14 April 2024

Lubina firefighters’ museum

The museum opened in the restored historic fire station in Miškech Dedinka, linked to the Blahej pamäti project. Local volunteers helped create the exhibition preserving the community’s firefighting tradition.

Source [18] ↗ Source [41] ↗
2023
Completion documented

Wifi pre Teba II

The notice records completion on 27 April 2023, ten outdoor access points and a €14,250 grant. Current network availability and connection quality need a separate check.

Source [19] ↗
2025
Scope and funding documented

Village-centre public space

The project notice describes renewal around the First World War memorial and the fire station. Eligible expenditure: €57,833.76; grant: €54,942.07. The notice alone does not establish handover of completed works.

Source [20] ↗
2025–2028
Project preparation; future dates are plans

Stará Turá–Lubina cycle path

The municipal project portal lists €2.1 million overall and envisages construction from summer 2027 to autumn 2028. Stará Turá’s June 2025 minutes report a €107,010 tender for design documentation. That is neither the full construction price nor an established cost borne by Lubina alone.

Source [21] ↗ Source [22] ↗
2026
Funding approved on 21 October 2026

Miškech Dedinka cultural-centre roof

Resolution 52/2026 allocates €6,000 from the reserve fund to repair the damaged roof. It documents a funding decision, not completion of the works.

Source [31] ↗
2025–2026
Purpose documented by the project page

Equipment for separate waste collection

The municipality published a project for a small tractor and equipment supporting separate waste collection. Assessment requires matching the final price, funding, handover and actual use.

Source [40] ↗
What will we track for projects?

Original budget → contract and amendments → paid invoices → deadline and handover → usage and annual operating costs. A grant or a high price alone does not establish whether a project offers good value.

New project coverage